The project is divided into three phases, replacing the roof areas with the poorest rating scheduled first. This includes approximately 19,835 SF of areas that require asbestos abatement.
The roof, flashings, drains, scuppers, joint sealants, exterior joints, and curbs will be demolished and replaced throughout this project. The lightning protection system will be removed and reinstalled upon completion of the project.